Liquid Overlay Systems.
Project Type(s): Centaur PU Waterproofing System Overlay to Asphalt
Location: North London
Value: Package
Duration: 4 Weeks
Date Completed: March 2022
Our Roofing Division were instructed to inspect, survey and subsequently undertake a Liquid Overlay System to a series of flat roofs to a property in North London using the Centaur PU waterproofing system.
The preparation for this project consisted of carrying out asphalt repairs as found necessary and jet washing the area complete.
The Centaur PU Waterproofing System was then applied which comprised of the Centaur primer, PU waterproofing with GFM reinforcement, followed by the PU top coat.
Photos:
Left: Before works commenced to the flat roofs.
Right: Centaur PU Waterproofing Application Completed.